The MIC and its partner NWRPC occasionally issue Requests for Proposals (RFPs) for specialized consultant services to augment current plans and studies.

Open RFPs, along with any addenda or updates, are published on this page. Inquiries or requests for clarification must be directed to the RFP Coordinator and all questions and answers will be posted here as public information. Proposers are responsible for checking back for updates for the duration of the RFP posting.


RFPs are now CLOSED for the following planning studies:

NWRPC-City of Superior Comprehensive Operational Analysis & Service Design Recommendations Study

April 4, 2014

The Northwest Regional Planning Commission (NWRPC) in Spooner WI, is seeking proposals from qualified consulting firms to conduct the City of Superior Comprehensive Operational Analysis & Service Design Recommendation Study.

The purpose of this study is to conduct a City of Superior comprehensive transit service performance analysis of the DTA’s current fixed route and paratransit systems with a major component being the service delivery study.

View Complete RFP Here

All proposals are due by 2:00 PM Central time on Thursday, May 8, 2014.

RFP Coordinator
Please address any questions about this RFP to Sheldon Johnson, NWRPC, 1400 South River Street, Spooner, WI 54801; Phone (715) 635-2197; or by email. This is the only person designated to answer questions regarding this RFP.


ADDENDUM #4
April 23, 2014

View summary of the April 17, 2014 Bid Conference
END OF ADDENDUM #4

ADDENDUM #3
April 23, 2014

Page 29 – Item #G-21, General Conditions & Mandatory Clauses section
Liquidated Damages as identified in G-21 has been dropped as a requirement from the RFP.
END OF ADDENDUM # 3

ADDENDUM #2
April 15, 2014

Page 2 – Item #8, Economy of Preparation section
Q: RFP notes that proposals are limited to 25 pages plus proposal sheet and required certificates. Can you please clarify what is and is not included in the 25 pages? Specifically, are staff resumes and profiles of relevant past work counted towards the 25 pages?

A: Required forms do not count as part of the 25 pages, resumes and descriptions of past work do count.

Page 4 – Scope of Work
Q: Product items in the scope of work suggest that this analysis is to be completed for the City of Superior. However, under "Consultant Duties" (page 6) it is noted that the Consultant shall conduct a COA of the entire system. Can you please clarify if this study addresses the full DTA transit system or just the portion in Superior?

A: Portion in Superior, including the Duluth/Superior route.

Page 6 - Process and Responsibilities
Q: Is the ridership and on–time performance survey work being completed just for routes in Superior or for the entire DTA system?

A: Portion in Superior, including the Duluth/Superior route.

Page 8, Proposal Content, Item #9
Q: The RFP notes that cost information is not to be included within the body of the technical response to the RFP. Does this mean that a cost proposal should be a separate submitted document, or that it should just be a separate section within the proposal (and included within the 25 page limit)?

A: Separate section, part of the 25 pages

Pages 17 through 23
Q: Pages 17 through 23 contain various required certificates that are to be included with a proposal submittal. Are those to be signed by just the prime consultant, or by sub consultants as well?

A: Prime must submit their signed copies.

Page 35, Item #35
Q: Item #35 identifies bonding requirements – equivalent to five percent of the bid price. Yet Section G-10 on page 26 notes that performance and payment bonds are only required for proposals that exceed $100,000. Can you clarify if a bond is required, to whom it should be made out to, and when a submitting firm might get that bond money back?

A: Proposal bond is required. It should be made out to NW Regional Planning Commission.
END OF ADDENDUM # 2

ADDENDUM #1
April 9, 2014

The April 17, 2014 10:00 am Bid Conference as identified on page 11 of the City of Superior Comprehensive Operational Analysis & Service Design Study is not required for consultant participation. This optional bid conference can be attended in person at the offices of the Duluth Transit Authority (DTA) located at 2402 W Michigan Street Duluth, MN 55806 or via conference telephone by calling 1-855-947-8255, pass code 7502005#.
END OF ADDENDUM # 1



Duluth International Airport Air Service and Air Cargo Leakage and Expansion Analysis
August 22, 2012

The Metropolitan Interstate Council (MIC), a division of the Arrowhead Regional Development Commission (ARDC), is seeking proposals from qualified consulting firms to conduct the Duluth International Airport Air Service and Air Cargo Leakage and Expansion Analysis.

The purpose of this study is to acquire and analyze data to identify future growth opportunities in both passenger air service and air cargo service at DLH and prospects to serve those markets.

View Complete RFP

All proposals are due by 4:30 PM Central time on Thursday, September 20, 2012.

RFP Coordinator
Responders who have any questions regarding this RFP please submit questions by e-mail to: Rondi Watson, RFP Coordinator. This is the only person designated to answer questions regarding this RFP.



Duluth-Superior Cruise Ship Terminal Facility Study
June 7, 2012

The Metropolitan Interstate Council (MIC), a division of the Arrowhead Regional Development Commission (ARDC), is seeking proposals from qualified consulting firms with engineering and planning expertise to conduct a Duluth-Superior Cruise Ship Terminal Facility Study.

The purpose of the Study is to investigate site options and budgetary considerations for the construction of a cruise ship terminal to accommodate new security requirements for passenger cruise ships visiting the Duluth-Superior port, with consideration of potential impacts on the local multimodal transportation system.

View complete RFP

All proposals are due by 3:00 PM local time on Friday, July 6, 2012.

RFP Coordinator
Responders who have any questions regarding this RFP please submit questions by e-mail to: Rondi Watson, RFP Coordinator. This is the only person designated to answer questions regarding this RFP.



Intersection Control Evaluation Planning Study for the Duluth Area
May 21, 2012

The Duluth-Superior Metropolitan Interstate Council, a division of the Arrowhead Regional Development Commission, is seeking responses from qualified consulting firms to the Request for Proposals for the Intersection Control Evaluation Planning Study for the Duluth Area.

Work will include analysis of eight selected intersections using the Minnesota Department of Transportation Intersection Control Evaluation (ICE) methodology; ICE reports prepared according to that format; preliminary roundabout concepts for up to three intersections, and an outline of a public education strategy to promote the benefits of roundabouts to the community.

View complete RFP

All proposals are due by 4:30 PM local time on Tuesday, June 19, 2012.

Modifications to Original RFP
The following Addenda have been issued to modify, explain or correct the original specifications and/or previous addenda and are hereby made a part of the Contract Documents.

ADDENDUM #3
June 28, 2012
NOTICE:
Due to the recent historic flood conditions and subsequent damage to public infrastructure throughout the City of Duluth and St. Louis County, the award of this contract will be delayed for 60 days after proposals were due, or until Friday, August 17th, 2012. It is anticipated that the scope of work will remain unchanged. The revised RFP timeline is as follows. Changes to the original RFP are noted in red:

Page 2:
It is anticipated that work described in this RFP will begin September 4, 2012 and be completed by February 1, 2013 .

Page 7:
May 21 — RFP posted
June 1 — Deadline for questions from potential Responders
June 6 — Responses to questions will be posted
June 19 — Deadline for RFP submittals
July 23-Aug 15 — Evaluation and scoring of RFP submittals
Aug 17 — Notification of successful bidder
Aug 20 - 31 — Contract finalized; Mn/DOT, FTA approvals
Sept 4, 2012 — Notice to proceed (pending execution of contract and agency approvals)
Feb 1, 2013 — Project completion


For proposals received by the June 19 deadline: if this delay does not meet the firm’s requirements in terms of pricing, personnel, or any other area of the proposal as submitted, please submit a document noting specific areas of change from the initial proposal. Mail one original and 6 copies to the RFP Coordinator at the address shown below by 2:00 pm on Wednesday, July 11.
END OF ADDENDUM # 3

ADDENDUM #2
June 6, 2012
NOTICE:
Only proposals from Consultants with personnel assigned to this project who have been pre-qualified by MN/DOT for roundabout design will be considered.
END OF ADDENDUM # 2

ADDENDUM #1
June 6, 2012
NOTICE: This Addendum is based on questions received by prospective Responders by June 1, 2012 and is issued to modify, explain or correct the original specifications, and is hereby made a part of the RFP and Contract Documents. Please attach this Addendum to the RFP and note receipt of this Addendum on the Request for Proposal.

Q: How many of the 8 intersections have current turning movement and hourly approach volume data?
A: The consultant will be responsible for obtaining the necessary intersection traffic data.

Q: What mapping information will be available to the consultants for the purpose of developing preliminary RAB concepts?
A: The consultant will have access to aerial imagery from St. Louis County.
END OF ADDENDUM # 1

RFP Coordinator
Responders who have any questions regarding this RFP please submit questions by e-mail to: Rondi Watson, RFP Coordinator. This is the only person designated to answer questions regarding this RFP.



Select a Font Size Set Display to the Normal Font Size Set Display to a Larger Font Size Set Display to the Largest Font Size

We Need Your Input!
Visual Representation of Surrounding Text

The MIC has prepared a Draft Long Range Transportation Plan (LRTP) for the Duluth-Superior Metropolitan Area for the next twenty five years.

You are invited to give input and learn about transportation trends, priorities and planned projects for Duluth, Superior, Hermantown, Proctor and area townships.

Public comments are being taken from September 1 through September 30, 2014 on the plan’s content and the proposed projects.

Three public meetings will be held, on:

Thursday, September 18th
, from 4:00 p.m. to 6:00 p.m. at the Superior Public Library

Thursday, September 25th from 4:00 p.m. to 6:00 p.m. at ARDC (Arrowhead Regional Development Commission) in Downtown Duluth.

Monday, September 29th,
from 4:00 p.m. to 7:00 p.m. at the Downtown Duluth Transit Center.

Questions and comments can also be directed to MIC Planner James Gittemeier by phone at (218) 529-7556 or by e-mail.


Current Planning Initiatives


4th Street Construction Project

Duluth-Superior Port Land Use Plan

Northwest Douglas County Freight Movement Study

Duluth 6th Avenue East Traffic Study

Bicycle Planning


Recent Plans and Studies
Grand Ave/State Hwy 23 Corridor Study

Superior South End Traffic Study

Intersection Control Evaluation (ICE) Study for the Duluth Area

Duluth-Superior Cruise Ship Terminal Study

DLH Air Service/Air Cargo Leakage & Expansion Analysis

Duluth Sidewalk Study

Duluth-Superior Metropolitan Bike Map

Central Entrance Corridor Study

Lincoln Park Pedestrian Plan

Transportation Systems Management (TSM)

N Minnesota/NW Wisconsin Freight Plan

UMD-CSS Transportation Study

East 2nd Street Corridor Study (Superior)

DTA Route Analysis for the City of Superior

Downtown Modal Connections Study

Proctor Comprehensive Plan Update 2008

Endion Land Use and Transportation Study

Safe Routes To School Funding Applications

Northwest Superior Traffic Circulation Plan

Proctor Master Trail Plan

Munger Trail to Lakewalk Connector


Erie Pier Management Plan

Duluth Heights Traffic Circulation Plan

MnDOT Functional Classification Update

Public Involvement Plan

Rice Lake Road Corridor & Traffic Impact Study

Duluth and Superior Safe Routes to School Plans

Duluth Urban Area Growth Impact Study

Human Services Coordinated Transit Plan